Previous Mining

Limits of mining

This map outlines the approximate distribution of previously mined ground on the claim block. Much of the initial mining by D.C. Klippert, including the discovery cut, occurred at the mouth of Dan's Pup and extended 2000 ft up the drainage. Reno Contracting Ltd., continued mining Dan's Pup and processed another 600 linear ft of the drainage before moving to upper Seattle Creek. Between 2016 and 2019, Reno Contracting Ltd. targeted shallow pay on upper Seattle Creek.     

Seattle Creek_Mined Areas.jpeg
461096986_2597545560633673_4428185339703583564_n.jpg

Production values

Between D.C. Klippert and Reno Contracting Ltd. approximately 2600 oz was mined from the lower 2600 ft of Dan's Pup. On upper Seattle Creek, Reno Contracting Ltd. extracted 700 oz.